Construction Schedule and Methodology for Kashiwazaki-Kariwa Unit No.6
  Shorter Construction Period Target
  Shortening the Construction Period at Kashiwazaki-Kariwa
  Milestones in the Construction of Unit No.6
Nuclear Energy Systems & Services Division
Home > Nuclear Power > Our Business >

The "more advanced" ABWR

 

Expanded Use of Equipment and Piping Modules


Expanded Use of Equipment and Piping Modules

Expanded Use of Equipment and Piping Modules

The volume of equipment, piping and supports in a nuclear power station is enormous, and so is the amount of fabrication usually done on site, most of it welding. With Unit No.6, Toshiba wanted to complete as much work as possible in advance of installation, so cutting down on time-intensive on-site work. The means to this lay in increased use of modules.
In addition to modules made up largely of pipes and supports, Toshiba developed modules bringing together high value-added equipment and cable conduits and instrumentation piping. These modules made a significant contribution to concurrent installation and construction.