2008

June:
Get the business license.
December:
Finish construction of factory.

2009

April:
Get certificate of ISO 9001-2008.
June:
First supply of T/L Lightning Arrester (EGLA) to PTC1 (Vietnam).
August:
First sales of relay made in Vietnam to Dong Nai PC (Vietnam)
November:
Get import-export license; First sales of substation surge arrester to ETC3 (Vietnam).

2010

May:
Get first overseas project of protection relay (Taiwan)

2011

January:
Get certificate of ISO 14001.
December:
Get of Substation Automation system for 220kV substation (SPPMB, Vietnam).

2012

June:
Start manufacture of GRE relay (New design for MV system).
July:
Start manufacture of G2 relay Generation Protection & control Device).

2013

July:
Get first order of 220kV transformer for two substations (NPPMB, Vietnam).

2014

August:
Get first order for complete Primary & Secondary equipment of 220kV substation (NPPMB, Vietnam)
September:
Get first order for complete Primary equipment including power transformer for Vietnamese 110kV substation of hydropower plant

2015

June:
Get first order for 500kV transformer (NPPMB, Vietnam)
October:
Relocation to the new factory (facility expansion)

2016

April:
Open Representative Office in Ho Chi Minh City
Successful completion of system engineering for 400kV Substation Automation System (Oman)
June:
Get first order for 500kV Substation Automation System (CPPMB, Vietnam)

Certificates

ISO9001:2008

ISO9001:2008

ISO14001:2015

ISO14001:2015

OHSAS18001:2007

OHSAS18001:2007

IEC TYPE TEST

IEC TYPE TEST

IEC61850 CERT

IEC61850 CERT
  • EVN(Vetnam).
  • TNB(Malaysia)
  • PLN(Indonesia)
  • ENA(UK)
  • Kesco(Korea)
  • EGAT(Thailand)